Chapter 11: Arsenic measurement procedure

This chapter describes the standard procedure used to measure dissolved arsenic using the OpenArsenic platform.

Chapter 11: Arsenic measurement procedure

11.1 Introduction

This chapter describes the standard procedure used to measure dissolved arsenic using the OpenArsenic platform.

The procedure outlined here represents the validated OpenArsenic workflow and should be followed whenever possible. Deviations from the procedure should be documented and may require additional validation.

The OpenArsenic method combines:

  • Electrochemical arsenic detection 
  • Standard addition calibration 
  • Replicate measurements 
  • Peak analysis 
  • Statistical evaluation 

Together, these steps provide a robust framework for quantifying arsenic in groundwater samples.

This chapter should be considered the primary Standard Operating Procedure (SOP) for routine arsenic analysis using OpenArsenic.

11.2 Overview of the workflow

A typical arsenic measurement consists of:

Figure 2. Sequence of steps used for routine arsenic analysis.

11.3 Before you begin

Before starting a measurement, verify:

Hardware Reagents Electrode Software
✔ Rodeostat connected
✔ Electrodes installed
✔ Stirrer operational
✔ OpenVoltam running
✔ Sample prepared
✔ 1 M HCl available
✔ Arsenic standard available
✔ Deionized water available
✔ Conditioned today
✔ No visible contamination
✔ Stable conditioning response
✔ Sample environment created
✔ Arsenic Detection method available

11.4 Creating the sample run

  • Open the desired sample environment.
  • Select: New Run
  • And follow the recommendations in the figure below
The OpenArsenic method recommends four repetitions whenever practical:
• Better reproducibility estimates
• Improved confidence intervals
• Identification of outliers
• Increased confidence in final results

Figure 11.1. Configuration of the initial sample measurement.

11.5 Running the measurement

Select: Ready to Run

Review the settings carefully. Then select: Begin Run

OpenVoltam will begin executing the measurement sequence. During acquisition:
✔ Observe the live voltammogram
✔ Verify normal software behavior
✔ Verify stable hardware operation
✔ Confirm stirrer operation during deposition
Avoid:
✘ Disconnecting the USB cable
✘ Moving electrodes
✘ Closing OpenVoltam
✘ Running resource-intensive software

Figure 11.2. Example live voltammogram displayed during measurement.

When acquisition finishes: review the voltammograms.
At this stage, focus on identifying obvious problems such as:
• Saturation
• Excessive noise
• Missing signal
• Communications errors

11.6 Peak analysis

When the run finishes:

  • Data are automatically stored 
  • Voltammograms are saved 
  • Results become available for analysis 

At this stage users may:

  1. Analyze the data immediately 
  2. Continue with additional measurements 
  3. Return later for analysis 
Figure 11.3: Completed run displayed in Sample Environment

When analysis begins, OpenVoltam automatically estimates:

  • Peak position 
  • Baseline location 
  • Start point 
  • End point 

This automation helps:

  • Reduce operator variability 
  • Increase consistency 
  • Speed up analysis 

For the current Caminos de Agua arsenic method, peaks typically occur between: -0.2 V and +0.1 V

However, this range may vary depending on electrode condition and sample matrix. After opening the analysis window:

  1. Review the automatically selected baseline. 
  2. Confirm that the full arsenic peak is included. 
  3. Verify that the baseline does not intersect the peak. 
  4. Check that the baseline extends beyond the peak region on both sides. 
Figure 11.4. Example of automatically selected baseline

Adjusting the Baseline

If the automatically selected baseline is not appropriate:

  1. Drag the first baseline marker to a more suitable location. 
  2. Press Z to move to the second baseline marker. 
  3. Adjust the second marker if necessary. 
  4. Verify that the baseline follows the underlying signal rather than the arsenic peak itself. 

Once satisfied: click Accept & Next and continue to the next repetition. After all repetitions have been analyzed:

  1. Click Save All 
  2. Return to the Sample Environment 

11.7 Performing standard addition 1 and 2

  • Once the sample measurement is complete, right-click the Sample run and select: New Run From Config
  • Change the Run Type from Sample to Standard Addition
  • Enter: Volume of arsenic standard added and Concentration of the added standard

Notes 🡺 Example: Well_A + 2.5 ppb As

Figure 11.5. Configuration of the first standard addition.

Selecting an appropriate spike

The first standard addition should produce a noticeable increase in signal while remaining within the linear working range of the method.

General recommendations:

  • Avoid extremely small additions. 
  • Avoid excessively large additions. 
  • Aim for a clear increase in peak height: we recommend adding 2.5 ppb arsenic. 

Examples and further guidance are provided in Chapter 12.

Running the standard addition measurements

  • Repeat the measurement using the same number of repetitions as the original sample.
  • Recommended: Four repetitions
  • Verify that acquisition proceeds normally.
  • When complete, review the voltammograms for obvious issues and analyse the peaks.

🡺 do the same for the second standard addition

11.8 Common problems during data acquisition

Issue Possible causes
No peak visible
  • Low arsenic concentration
  • Poor electrode condition
  • Incorrect settings
Excessive noise
  • Loose connections
  • Electrical interference
  • Poor electrode contact
Unstable signal
  • Electrode movement
  • Reference electrode problems
  • Stirring issues
Saturation
  • Incorrect current range
  • Hardware issues